Microsoft Office TrainingThe UK's Number 1 for Microsoft Office Training Sitemap add this page to your favourites/bookmarksBookmark page
 
view a printable version of this pagePrintable version
Plus One Google
Customer: Sign in
Delegate: Sign in
Trainer: Log in

articleWhy Do Project Tasks Change Duration Automatically?

Why does Project change the task duration automatically? This article explores the feature called Effort Driven.
Working with Microsoft Project, have you ever come across one of these "tear your hair out" moments? You're working with Project tasks, and you've just changed how many staff you've assigned to a particular task because you've had a rethink or perhaps you need to deploy staff in a different way. What does Project do - it changes the task duration! After all the work you did figuring out the best task duration in the first place.

The answer lies of course in a Project feature called EFFORT DRIVEN. It works this way. Suppose you have a two task project, "give a presentation" and "analyse feedback forms". The presentation itself is to take four hours to deliver, so you set its task duration to 4 hours. You then assign Fred to give the presentation. Project now calculates the WORK to be done on the task as 4 hours times 1 resource unit (Fred), equals 4 HourUnits. Project doesn't worry about what kind of resource you've assigned to the task, just how many are initially assigned.

EFFORT DRIVEN means that if you subsequently change the allocated resources, Project will keep the total WORK for the task at the original level set when the first resource was assigned. So if you assign Mary to help Fred give the presentation, there are now two resource units assigned to the task. So in order to keep the total WORK at 4 HourUnits, Project changes the task duration to two hours, so the WORK is still 2hr times 2 resource units, equals 4 HourUnits. However our presentation duration must be 4 hours, So you manually change the task duration back to 4 hours. Of course the WORK to complete this task is now increased to 8 HourUnits.

The second task "analyse feedback forms" is done immediately after the presentation in the same room and involves collecting a completed audience questionnaire and then counting how many particular survey questions were ticked. You expect this to take two hours and you assign Jane to do this work. So The WORK for this task is 2hrs times 1 resource unit making 2 HourUnits.

You might want to get this analyses work done as quickly as possible as you want to vacate the room as soon as you can and all head off home, so you assign Bill to help Jane. Once you assign Bill to the task Project applies the same EFFORT DRIVEN principle. So in order to keep to the original WORK at 2 HourUnits it reduces the task duration to 1 hour. So now the WORK is still 2HourUnits - 1 hr times 2 resource units (Jane and Bill). And this time this makes sense to you - two staff should complete this task in half the time, so Jane and Bill should complete this task in one hour.

In Project, some tasks do behave this way - for example two staff can clear some shelves in half the time as it takes one member of staff. However other tasks do not. For example if 3 staff are scheduled to attend a one day meeting and you subsequently ask three additional staff to attend the same meeting, the meeting duration should not, perhaps unfortunately, reduce by half - it remains at the original duration.

Microsoft Project has traditionally been used in the construction/building industry where generally speaking many tasks are EFFORT DRIVEN. So Project sets all tasks to be EFFORT DRIVEN by default. However Project is now used in many different project situations involving managing tasks, people, other resources and costs where tasks do not necessarily behave in this way. So if you are starting a brand new project you need to decide if you want tasks to be EFFORT DRIVEN or not, or a mixture.

If you want all task durations to stay the same even if you change assigned resources you can turn off Project's default EFFORT DRIVEN setting and instead set all tasks to be "Fixed Duration". This means that if you change the resources assigned to the task, its duration will stay the same. If you want to change the EFFORT DRIVEN settings for all tasks in a particular Project, before the tasks are entered, ensure the application is open, then choose Tools, Options and select the Schedule tab.

Alternatively if you leave Project's default settings alone, so EFFORT DRIVEN is on, you can turn EFFORT DRIVEN off for individual tasks. This is done by double clicking a task and in the task information panel choose the Advanced tab.

The key to understanding EFFORT DRIVEN is to bear in mind what happens to the task duration if you change the assigned resource after the first resource has been assigned.

So hopefully you'll no longer be surprised if Microsoft Project changes a task duration automatically - it's because the task is EFFORT DRIVEN. Consider building up further skills in using Project by attending an instructor lead training course. The best ones are hands on and very instructive.

Author is a freelance copywriter. For more information on project.training, please visit http://www.microsofttraining.net


Original article appears here:
http://www.microsofttraining.net/article-764-why-do-project-tasks-change-duration-automatically.html


Back to article list

Distribution notes

PUBLICATION GUIDELINES

  • You have permission to publish this article for free providing the "About the Author" box is included in its entirety.
  • Do not post/reprint this article in any site or publication that contains hate, violence, porn, warez, or supports illegal activity.
  • Do not use this article in violation of the US CAN-SPAM Act. If sent by email, this article must be delivered to opt-in subscribers only.
  • If you publish this article in a format that supports linking, please ensure that all URLs and email addresses are active links, without the rel='nofollow' tag.
  • Software Training London Ltd. owns this article. Please respect the author's copyright and above publication guidelines.
  • If you do not agree to these terms, please do not use this article.

Rate this page:
2.8/5 (129 votes cast)
Accredited Training Provider: Institute of IT Training Institute of Leadership and Management - Certified Courses
Microsoft Certified Partner
Security Seal verified by visa, mastercard securecard

Mini sitemap. These are the main areas of our web site. Full sitemap.

Management training

Professional Skills courses
Project Management Course London
Project Management Courses London
Project Management Training London
Project Management Training
Project Seminar
Project Seminars
Time Management Course London
Time Management London
Time Management Courses London
Time Management Training London
Introduction to Finance course
Assertiveness Skills course
Effective Communications Skills training
Presentation Skills London

Training Formats

Public scheduled courses
On-site training
Closed company courses

Consultancy
Application Development

Blogs

Excel Training
MS Project Training
Microsoft Training Blog

Version differences

Office 2010 vs 2007
MS Project version differences

Training Information

London Computer Training
Computer Training London
Docklands Training Courses
Docklands Training London

Training venues London
Client list
FAQ
Pricing and availability
Course details / Syllabus

Training Articles
Training Information

Microsoft training

Microsoft Office training
& IT Applications

Microsoft Project training
Microsoft Outlook training
Microsoft Powerpoint training
Microsoft Word training
MS Project courses
MS Project training
Outlook courses
PowerPoint courses
PowerPoint training
VBA courses
Word courses
Microsoft.training
(more...)

Excel Training

Excel courses
Excel Training Courses Medway
Autonumber in Excel
Microsoft Excel training
Basic Excel Courses
Basic Excel Course
Basic Excel Training

Interested in MS Access training?

Access courses
Microsoft Access training
Microsoft access courses
Microsoft training access course
Microsoft+access+training
Access courses in london

Training provider

Training providers
IT training companies
IT training providers
Management Training providers
Management Training provider

Event history, feedback results
Events in 2012 · 2011 · 2010 · More

See also

Crystal Reports training