articleUnderstanding Critical Path In Project

Do you want to learn what the critical path means in Microsoft Project? This article describes what the critical path is and shows you how to format the Gantt chart to show the critical path.
When you start using Microsoft Project to build project plans, you create and link tasks to show the project steps. You may have heard the term "critical path" in relation to the tasks, but what exactly does this mean? This article describes what the critical actually means, how to show the critical path in your Gantt charts and explains why it's so important.

A task is described as critical if changing its duration changes the duration of the entire project. So if you create and save a project file consisting of four tasks in series, then the overall project duration is the sum of the durations of the four tasks. If you change the duration of any of the tasks, then the entire project duration will change. Each of the four tasks are critical, and the path from start to finish through the four tasks is called the critical path. Changing any task duration on the critical path changes the project entire duration.

Suppose you've created and saved a different project plan, this time with two parallel sets of tasks which link to a final completion task. The upper of the parallel paths has longer task durations than the lower parallel path. Now when you work out the overall project duration, this depends on the longer of the two parallel paths. So all the tasks from start to finish through the longer path add up to make the overall project duration, and this is the critical path.

So basically the critical path is the flow of tasks from project start to finish, through the longest task duration options. If any task duration on the critical path is changed then the entire project duration changes.

The Gantt chart view can be formatted to show this critical path. We'll start with a four task project, all linked serially, so the links are all finish to start relationships, and each task duration is 2 days. So the total project duration is 8 days. You can turn on the Project Summary Task to show this - choose Tools, Options, View tab and tick "Show project summary task" in the lower left of the panel, and click OK to finish.

Now we'll format the Gantt chart to show the critical path. To do this click the "Gantt Chart Wizard" toolbar button. In the Gantt Chart Wizard click Next, then select critical path and click Next, accept resources and dates and click Next, accept yes for the line links, and click Next, then click the Format it button, and click Exit wizard to finish. You'll see that all four task are coloured red for critical. Try increasing one of the task durations and of course the entire project duration changes and all tasks stay red.

Now try the same exercise with the other example project with the two parallel paths. With the task displayed in the Gantt chart, again set Project to format the critical path as red using the Gantt chart wizard in the same way as we described earlier. When this has been formatted, you'll see that only the tasks from the start through the longer of the two parallel paths to the final task are shown in red as critical. So the critical path is the flow of tasks through the longer path, and changing the duration of one of these tasks affects the entire project duration.

Try changing the duration of one of the tasks in the shorter parallel path. Provided that the duration of the shorter path remains less than the longer path you'll see that this does not affect overall project duration and the shorter tasks remain non critical blue.

If you change one of more on the task durations in the shorter path until the duration of the shorter path becomes more than the duration of the longer path, the critical path will switch and the new longer parallel path becomes red and the other reverts back to blue.

Knowing the critical path tasks is essential in project management so resources can be assigned to tasks in the most efficient way. For example if a project duration must be reduced by a certain number of days, then we could assign more resources to a critical path so that it can be completed more quickly and hence reduce the overall project duration. We could also reduce some resources on non critical tasks, so that they take longer to complete without affecting the overall project duration and reassign them elsewhere on critical tasks.

You may be interested in learning more about Project critical paths and Microsoft Project in general. You'll find that there lots of courses available to help you increase your skills. The best ones offer clear explanations with lots of hands on exercises, so why not consider one. You'll not regret it.

Author is a freelance copywriter. For more information on ms project training, please visit http://www.microsofttraining.net


Original article appears here:
http://www.microsofttraining.net/article-905-understanding-critical-path-in-project.html


Back to article list

Distribution notes

PUBLICATION GUIDELINES

  • You have permission to publish this article for free providing the "About the Author" box is included in its entirety.
  • Do not post/reprint this article in any site or publication that contains hate, violence, porn, warez, or supports illegal activity.
  • Do not use this article in violation of the US CAN-SPAM Act. If sent by email, this article must be delivered to opt-in subscribers only.
  • If you publish this article in a format that supports linking, please ensure that all URLs and email addresses are active links, without the rel='nofollow' tag.
  • Software Training London Ltd. owns this article. Please respect the author's copyright and above publication guidelines.
  • If you do not agree to these terms, please do not use this article.

Rate this page:
2.8/5 (129 votes cast)
Accredited Training Provider: Institute of IT Training Institute of Leadership and Management - Certified Courses
Microsoft Certified Partner
Security Seal verified by visa, mastercard securecard

Mini sitemap. These are the main areas of our web site. Full sitemap.

Management training

Professional Skills courses
Project Management Course London
Project Management Courses London
Project Management Training London
Project Management Training
Project Seminar
Project Seminars
Time Management Course London
Time Management London
Time Management Courses London
Time Management Training London
Introduction to Finance course
Assertiveness Skills course
Effective Communications Skills training
Presentation Skills London

Training Formats

Public scheduled courses
On-site training
Closed company courses

Consultancy
Application Development

Blogs

Excel Training
MS Project Training
Microsoft Training Blog

Version differences

Office 2010 vs 2007
MS Project version differences

Training Information

London Computer Training
Computer Training London
Docklands Training Courses
Docklands Training London

Training venues London
Client list
FAQ
Pricing and availability
Course details / Syllabus

Training Articles
Training Information

Microsoft training

Microsoft Office training
& IT Applications

Microsoft Project training
Microsoft Outlook training
Microsoft Powerpoint training
Microsoft Word training
MS Project courses
MS Project training
Outlook courses
PowerPoint courses
PowerPoint training
VBA courses
Word courses
Microsoft.training
(more...)

Excel Training

Excel courses
Excel Training Courses Medway
Autonumber in Excel
Microsoft Excel training
Basic Excel Courses
Basic Excel Course
Basic Excel Training

Interested in MS Access training?

Access courses
Microsoft Access training
Microsoft access courses
Microsoft training access course
Microsoft+access+training
Access courses in london

Training provider

Training providers
IT training companies
IT training providers
Management Training providers
Management Training provider

Event history, feedback results
Events in 2012 · 2011 · 2010 · More

See also

Crystal Reports training