replyReply Sat 2 Feb 2008, 17:30Delegate Mark said...

Mark has attended:
Project Intermediate course

Microsft Project

Please explain how to change the whole gannt chart if the project start date changes from the date originally put in

For upcoming training course dates see: Pricing & availability

replyReply Sat 9 Feb 2008, 10:37Trainer Stephen said...

RE: Microsft Project

Hi Mark

Thank you for your question

The easiest method is to simply choose a new start date by going to Project-Project information and altering the start date combo box.

If however your project has been baselined you may want to remove the baseline and then reset it afterwards if you do not want the new start date to cause variances in your project

Regards

Stephen

 

Ms project tip:

Use Autofill in MS Project

a. Complete 1st entry
b. Select cell with entry to be copied
c. Click & drag autofill handle over the lines to also contain the same information. (the autofill handle is the little black square in the bottom right hand corner of the heavy lack outline on the selected cell)