Duplicate Milestones

resolvedResolved · Low Priority · Version Standard

replyReply Thu 20 Mar 2008, 16:06Delegate Claire said...

Claire has attended:
Project Intro Intermediate course
Excel Introduction course
Excel Intermediate course

Duplicate Milestones

The project I am currently working on is about 25 pages long. At the very top of the sheet I have a summary of the main milestones and then lower down I have the milestones again- this time they are separated out and are underneath the heading of the project that they relate to.

I would like a way to link the two task so that when I change the milestone in the summary section the duplicate milestone lower down also changee. I have tried linking them by start to start and finish to finish but this hasn't worked. Please help!

For upcoming training course dates see: Pricing & availability

replyReply Thu 27 Mar 2008, 11:30Trainer Andrew said...

RE: Duplicate Milestones

Hi Claire

thanks for describing the problem you are encountering.

From your description it sounds like the top part of your plan is made up of a top level summary - and below is the full detailed plan.

The milestones in the summary also appear in the full plan.
Changing a date in the summary should move the corresponding milestone in the detail (or vice verse).

This presents a challenge as you are having to keep two sets of the same data (both sets of milestones) up to date.

One approach is to do away with the summary altogether. When you want to see just the milestones use the built in filter
(Project Menu then Filtered For > Milestones)

You can then revert to see all tasks by going to Project > Filtered for > All tasks.

If you find the summary tasks clutter up the filtered display you can temporarily turn them off
Tools > Options > View tab and remove the tick from Show Summary Tasks.

I hope this helps. If not please let us know.

Kind regards,

Andrew

 

Please browse our web site to find out more about
ms project training and other Microsoft training courses.

Ms project tip:

Entering Days

To type in a day of the week, or its three letter abbreviation, in a Date field type "Monday" or "Mon", and Project will show the date for the next Monday after the current date.

View all MS Project hints and tips


Microsoft Certified Partner Accredited Training Provider: Institute of IT Training Institute of Leadership and Management - Certified Courses Security Seal verified by visa, mastercard securecard