msp progress
Microsoft Office Training verified by visa - mastercard securecode about microsoft training company london ukadd this page to your favourites/bookmarksAdd to favourites
view a printable version of this pagePrintable version
email this page to somebodyEmail this page
Customer: Sign in
Delegate: Sign in
Trainer: Log in

Forum home » Delegate support and help forum » Microsoft Project Training and help » MSP Progress

MSP Progress

The UK's most regular instructor-led training courses.
Training information: project server consultant · Project training · Microsoft Project Training uk
See also · microsoft project training courses · microsoft.project.course · microsoft+project+courses

resolvedResolved · Low Priority · Version Standard

MSP Progress

Stephen has attended:
Project Intro Intermediate course
Excel Introduction course
Excel Intermediate course
Excel Advanced course
Project Advanced course

by - delegate Stephen [15 posts] (2008 Mar 25 Tue, 15:56) replyReply

I'd like to show remaining work rescheduled to the status date rather than behind it. However when I check what I think are the right boxes in tools-options-calculations, the task bars don't split. Remaining work is still shown behind the status date. What should I do please?

Second question!
I have 4 milestones, 3 of which are set to 100% complete and one 0% not complete. The summary task for the 4 milestones shows 99% complete (!!!) and the progress line for the summary task zooms off to the right. Surely not right!

Thank you!

Project Intro Intermediate 2 day course
Version Date Location Places
available
Book Next place rate:
Card Invoice
2003 2008 Nov 24 Mon + 25 Tue Southwark 4 book now £475 £485
2007 2008 Nov 27 Thu + 28 Fri Bayswater 0 FULL    
2007 2008 Dec 8 Mon + 9 Tue Bloomsbury 0 FULL    
2003 2008 Dec 9 Tue + 10 Wed Bayswater 6 book now £335 £365
2007 2008 Dec 11 Thu + 12 Fri Bloomsbury 1 book now £490 £495
2003 2008 Dec 18 Thu + 19 Fri Southwark 7 book now £345 £399
Full Schedule: See all 55 Project Intro Intermediate course dates.
Bookings currently available until 26th November 2009.

RE: MSP Progress

by - trainer Andrew platinum contributer[513 posts] (2008 Mar 27 Thu, 11:45) replyReply

Hi Stephen

Let's focus in on a very simple project (one task!) to explore the possible settings.

- create a one task project
- set the task duration to 10 days
- set the status date to 5 days from now (Project > Project information > Status date)
- enable Project to shift uncompleted work to the status date (Tools > Options > Calculation). Start off by ticking
"Move start of remaining parts before status date forward to status date"

Now go back to your solitary task, double click it and on the General tab set its progress to 10%

Project should respond by marking off one day (10%) as complete the remainder should now be moved to start at whatever date you have set as the status date. Both parts of the task are linked by a split (dotted) line.

When you have finished wtih the status date go back into Project > Project Information and set the status date back to NA.

Does this get close to the outcome you were expecting?

PS if Status Date is set to NA (which it is by default) Project uses the Current Date value to work out where to move uncompleted work.

I will reply to your second question in a fresh post.

Kind regards,

Andrew


RE: MSP Progress

by - trainer Andrew platinum contributer[513 posts] (2008 Mar 27 Thu, 11:55) replyReply

Hi Stephen

With regard to your second question:
"I have 4 milestones, 3 of which are set to 100% complete and one 0% not complete. The summary task for the 4 milestones shows 99% complete (!!!) and the progress line for the summary task zooms off to the right. Surely not right!"

Very interesting. If I try to recreate your example
(summary task plus 4 milestones indented below it) Progress is 0% until all 4 are marked 100% when the summary task shows 100% completion too. It seems to be all or nothing rather than a cumulative calculation.

One thing that did make a difference though is if a task has been marked as milestone and progress has been recorded against it.

Double click on any regular task with a duration and on the Advanced tab tick the box (lower right corner) to mark the task as a milestone.

On the Gantt chart the task appears as a milestone with some Lag but now you can have degrees of progress that roll up to the summary task.

Does this describe the situation you are encountering? You might like to try checking each of your milestones to see if they are in fact tasks with durations that have been marked as milestones.

Let me know how you get on.

Kind regards,

Andrew


Related articles

· Three Ways to Make Microsoft Projects Courses More Effective
· Discover Microsoft Project 2003
· Why Very Small Businesses Benefit from Microsoft Project Training Seminars
· Reasons to Undertake Microsoft Project Training
· Microsoft Project Training Courses

Please browse our web site to find out more about
project server consultant and other Microsoft training courses.

Project tip:

Show or hide toolbar ScreenTips

On the Tools menu, go to Customize, and then select Toolbars.
Click the Options tab.
put a tick or remove the tick from the Show ScreenTips on toolbars check box.

View all Project hints and tips

Institute of IT Training - Accredited Training Provider Microsoft Certified Partner
microsoft office
Microsoft Office Specialist Authorised Testing Centre (MOS and MCAS)

Prodigy Platinum Learning Partner

Institute of IT Training - Accredited Training Provider Association of Computer Trainers Valid HTML 4.01 Transitional
Valid CSS Markup

secure online payments - visa - mastercard

Mini sitemap. These are the main areas of our web site. Full sitemap.

Training by application Main information pages See also

Access courses
DreamWeaver courses
Excel courses
MS Project courses
Outlook courses
PowerPoint courses
VBA courses
Word courses
(more...)

Public scheduled courses
On-site training
Closed company courses

Microsoft Office training
Pricing and availability
Training schedule
Training venues

Access training
Dreamweaver training
Excel training
MS Project training
PowerPoint training

London Computer Training
Computer Training London

Microsoft Access training
Microsoft Excel training
Microsoft Project training
Microsoft Outlook training
Microsoft Powerpoint training
Microsoft Word training

Time Management Course London

Interested in Access training? Please see the following pages:
microsoft access courses · microsoft training access course
microsoft+access+training · access courses in london

Training Information

Training Articles

AddThis Social Bookmark Button What's this?
Add to Del.icio.us Add to Facebook Add to Digg Add to Reddit Add to Google Add to Yahoo Add to Diigo Add to Mr. Wong Add to Linkarena Add to Power Oldie Add to Folkd Add to Jumptags Add to Upchuckr Add to Simpy Add to StumbleUpon Add to Slashdot Add to Netscape Add to Furl Add to Spurl Add to Blinklist Add to Blogmarks Add to Technorati Add to Newsvine Add to Blinkbits Add to Ma.Gnolia Add to Smarking Add to Netvouz