all my questions have
The UK's Number 1 for Microsoft Office Training Add this page to your favourites/bookmarksBookmark page
 
View printable version of pagePrintable version
Plus One Google
Customer: Sign in
Delegate: Sign in
Trainer: Log in

Forum home » Delegate support and help forum » Microsoft Project Training and help » All my questions have been answered - for now!

All my questions have been answered - for now!

resolvedResolved · Low Priority · Version Standard

replyReply Fri 28 Mar 2008, 16:19Delegate Josh said...

Josh has attended:
Project Intro Intermediate course

All my questions have been answered - for now!

All my questions have been answered - for now!

For upcoming training course dates see: Pricing & availability

 

Please browse our web site to find out more about
project server courses and other Microsoft training courses.

Ms project tip:

Link tasks using predecessor column - project

a. First, note ID number of the task you want to link to (predecessor). Then, in the predecessor column of the task you want to link to (successor), type the predecessor task's ID number.
b. The link will be a Finish to Start (the default type).
c. Or you can add in a code for a different relationship type
i. SS = Start to Start
ii. FF = Finish to Finish
iii. SF = Start to Finish
d. You don't have to type the task ID numbers in any specific order, but you must separate multiple tasks with commas.