Resource Pool

resolvedResolved · Low Priority · Version 2007

replyReply Tue 8 Apr 2008, 15:52Delegate Peter said...

Peter has attended:
Project Intro Intermediate course

Resource Pool

Will I experience any problems changing resource %ages on projects drawing from the resource pool, then levelling? What sort of things should I bear in mind, and what common pitfalls are there?

For upcoming training course dates see: Pricing & availability

replyReply Sun 18 May 2008, 19:01Trainer Alan said...

RE: Resource Pool

You will not be able to increase % allocation above the maximum level for resources shown in the pool but there should be no problems otherwise with changing percentages.

When levelling the pool however, there may be strange effects on work allocation - always check the hours allocated in Resource Usgae view!

 

Please browse our web site to find out more about
project server courses and other Microsoft training courses.

Ms project tip:

Inserting Task Durations Quickly

When entering durations for your tasks simply use the single letters - m for min, h for hr, d for day, w for week, but mon for month. If default is set for days, you need only type the number, for example 3 for 3days, or 0.5 for half a day.

View all MS Project hints and tips