Forum home » Delegate support and help forum » Microsoft Project Training and help » Baseline views

Baseline views

resolvedResolved · Low Priority · Version 2003

replyReply Wed 9 Apr 2008, 12:02Delegate Anne said...

Anne has attended:
Project Introduction course

Baseline views

how do I display the dates / times of all saved baseline views in the task pane.

For upcoming training course dates see: Pricing & availability

replyReply Sun 18 May 2008, 18:56Trainer Alan said...

RE: baseline views

You can't! Change to the Multiple Baselines Gannt view to see all start and finish dates or create a custom table incorporating the relevant Baseline fields, from which you can create a custom report.

 

Please browse our web site to find out more about
project server consulting and other Microsoft training courses.

Ms project tip:

Inserting Task Durations Quickly

When entering durations for your tasks simply use the single letters - m for min, h for hr, d for day, w for week, but mon for month. If default is set for days, you need only type the number, for example 3 for 3days, or 0.5 for half a day.

View all MS Project hints and tips


Microsoft Certified Partner Accredited Training Provider: Institute of IT Training Institute of Leadership and Management - Certified Courses Security Seal verified by visa, mastercard securecard