Part-time resource

resolvedResolved · Low Priority · Version 2003

replyReply Tue 29 Apr 2008, 15:41Delegate Jane said...

Jane has attended:
Project Introduction course
Project Intermediate course

Part-time resource

What's the best way to plan resources who will be working part-time on the project, when they do not work on fixed days each week? Using percentages gets very complicated. Is there a simpler option?

For upcoming training course dates see: Pricing & availability

replyReply Sun 18 May 2008, 17:56Trainer Alan said...

RE: part-time resource

Sorry Jane, but no.

The practical way is to ensure they are in the Resource Sheet as a percentage. Make sure the resource calendar is the Standard calendar. Then after you allocate them to a task, go to Resource Usage view and manually edit the working hours which Project has assigned.

replyReply Tue 20 May 2008, 11:41Delegate Jane said...

RE: part-time resource

Thanks Alan,

I suspected that was the case!

 

Please browse our web site to find out more about
project server course and other Microsoft training courses.

Ms project tip:

Create own ribbon tab - Project 2010

a. In Project click on the File tab
b. Select Options from left hand side
c. Choose the Customize Ribbon section
d. Click the New Tab button (below the list of tabs on the right hand side of the dialog box)
e. Select the New Tab (Custom) and enter a name, by clicking the Rename button (below the list of tabs on the right hand side of the dialog box)
f. Select the New Group (Custom) and enter a name, by clicking the Rename button (below the list of tabs on the right hand side of the dialog box)
g. Add commands to your tab and group by locating them on the list on the right hand side (remembering that you can change the list using the drop down box at the top of the list of commands) and clicking the Add button between the two panes to add them to your tab and group
h. You can rearrange the commands in your group, the groups on any tab or the tabs, using the up and down arrow buttons beside the list of tabs.
i. Click OK to apply your changes

View all MS Project hints and tips


Microsoft Certified Partner Accredited Training Provider: Institute of IT Training Institute of Leadership and Management - Certified Courses Security Seal verified by visa, mastercard securecard