Project Intro Intermediate course
Baseline
how will we compare where we are now with the baseline schedule?
For upcoming training course dates see: Pricing & availability
RE: baseline
Hi Darya
A quick way to compare your current position and the baseline is to switch to a view that shows both. If you go to the view menu and choose Tracking Gantt from the list you will see a display showing your baseline values (in grey) below your current plan.
Let us know if you have any further questions.
Kind regards,
Andrew
|