Forum home » Delegate support and help forum » Microsoft Project Training and help » Milestones/meetings
Milestones/meetings
Resolved · Medium Priority · Version 2003
Tracey has attended:
Project Intro Intermediate course
Milestones/meetings
we entered milestones for weekly reoccuring meetings. is it possible to do something very similar but without the milestones in order to avoid confusion from other viewers?
For upcoming training course dates see: Pricing & availability
RE: milestones/meetings
Hi Tracey
Sure - when you go to Insert > Recurring task you can choose the duration to suit. Rather than a milestone with 0 days duration you could set something more appropriate to your organisation. By default recurring tasks are set to 1 day duration but you might choose 1h (hour) or .5 (half a day)
Hope this helps - let us know if you have any other questions.
Kind regards,
Andrew
|