Resources
Resolved · Low Priority · Version 2003
Emily has attended:
Project Intro Intermediate course
Resources
Can you specify a resource as a room, which can only be used by one task at a time?
For upcoming training course dates see: Pricing & availability
RE: Resources
Hi Emily
Yes you can. In Project 2003 there are two type of resource - Work and material. Setting a room resource as Work will enable you to spot if it's been overallocated in your schedule.
Hope this helps - let us know if you have any further questions.
Kind regards,
Andrew
|