Working time

resolvedResolved · Medium Priority · Version 2003

replyReply Mon 12 May 2008, 15:04Delegate Simona said...

Simona has attended:
Project Intro Intermediate course
Project Advanced course

Working time

I want to change working time to 24 h, so I am going to tools, change working time and selecting 24h calender, but before doing that , do I have to select all columns that have the time, because if just change it without selecting all date, when I access calendar again, it displays default calendar, can you explain how to handle this tool, regards, Simona

For upcoming training course dates see: Pricing & availability

replyReply Sun 18 May 2008, 18:07Trainer Alan said...

RE: Working time

If you already have tasks in your project, you cannot change the working time for these.

You need to define the 24 hour calendar BEFORE entering tasks.

 

Please browse our web site to find out more about
project server consultant and other Microsoft training courses.

Ms project tip:

Format individual bars on your GANTT chart

To draw attention to a bar on your Gantt chart simply double click it. From the dialogue box that opens make your selection of text and bar modifications.

View all MS Project hints and tips


Microsoft Certified Partner Accredited Training Provider: Institute of IT Training Institute of Leadership and Management - Certified Courses Security Seal verified by visa, mastercard securecard