Start to finish relationship

resolvedResolved · Low Priority · Version 2003

replyReply Mon 12 May 2008, 16:29Delegate Laura said...

Laura has attended:
Project Intro Intermediate course

Start to finish relationship

Is there a simple way to determine or remember which of the following linking relationships to use: start to finish, finish to start, start to start, finish to finish?

For upcoming training course dates see: Pricing & availability

replyReply Wed 14 May 2008, 13:29Trainer Andrew said...

RE: Start to finish relationship

Hi Laura

A straightforward way of finding the right link between two tasks is first to decide which one is doing the driving or positioning of the other task on the Gantt chart. The driving task is the predecessor, the other task is your successor.

Double click on the successor and from the predecessor tab choose your driving task.

Next we need to decide the link. Ask yourself is it the start or finish of the predecessor that's doing the driving. Then does that affect the start or finish of your successor? That will guide you as to which type might be best for your tasks. Lastly you can add any lag required.

I hope this is helpful - do let us know if you need any further information.

Kind regards,

Andrew

 

Please browse our web site to find out more about
ms.project.courses and other Microsoft training courses.

Ms project tip:

Typing Links Between Tasks

In the Entry table, use the Precessors column to type in links. Type the previous task's ID to link. To change the link, add FS (Finish-Start), FF (Finish-Finish), and so on, and + duration to add a Lag, or - duration for a Lead time. Example: for task 5, 4FS+1w ... task 4 preceeds task 5, finish to start, with a week lag between.