Forum home » Delegate support and help forum » Microsoft Project Training and help » Extra time to a task

Extra time to a task

resolvedResolved · Low Priority · Version 2003

replyReply Mon 12 May 2008, 16:30Delegate Jo said...

Jo has attended:
Project Intro Intermediate course

Extra time to a task

How do you add extra 'buffer' time to a task / reduce time on a task - not the number of days.

For upcoming training course dates see: Pricing & availability

replyReply Wed 14 May 2008, 13:41Trainer Andrew said...

RE: Extra time to a task

Hi Jo

If I understand you correctly you might want to adjust how much work a resource will be carrying out on a task e.g. allowing 5 days duration for a task that takes perhaps an hour per day.

You can achieve this by switching to Resource Usage view and editing the assigned work for each task on a day by day basis.

I hope this is helpful. If you have any other questions please do not hesitate to contact us.

Kind regards,

Andrew

 

Please browse our web site to find out more about
microsoft projects courses and other Microsoft training courses.

Ms project tip:

MS Project 2010 Scroll to Task

Ever feel lost on a large project file? In Gantt view, Task ribbon, Editing, click on the Scroll to Task tool to centre the task bar on your screen.

Shortcut Ctrl+Shift+F5

Same as Go to Selected Task in MS Project 2003.

View all MS Project hints and tips


Microsoft Certified Partner Accredited Training Provider: Institute of IT Training Institute of Leadership and Management - Certified Courses Security Seal verified by visa, mastercard securecard