Project 2007 predecessors

resolvedResolved · Urgent Priority · Version 2007

replyReply Wed 21 May 2008, 19:28Delegate Emma said...

Emma has attended:
Project Intro Intermediate course

Project 2007 predecessors

Hi

For some reason, when I know change a predecessor on my project, it does not update any other fields.

Therefore, if I change durations etc on my plan, no other items are effected.

It seems fine in new workbooks, just my existing workbook which was okay until midway through today.

Any suggestions please?
Thanks
Emma

For upcoming training course dates see: Pricing & availability

replyReply Fri 30 May 2008, 16:58Trainer Stephen said...

RE: Project 2007 predecessors

Hi Emma

Thank you for your question

The first thing to check is whether your system is set for manual or automatic calculation.

Go to Tools-Options and select the calculation tab. At the top check to see if calculation is set to automatic or manual. If the latter, then this will explain your problem, as you have to click the "Calculate Now" button to update the consequences of any changes. If this is the case, setting the option back to automatic will resolve the issue.

If this is not the case, please let me know so I can look at other options

Regards

Stephen

replyReply Fri 30 May 2008, 17:50Delegate Emma said...

RE: Project 2007 predecessors

Thanks Stephen. I've sorted this out now - I had a circular reference in my predecessors
Emma

 

Please browse our web site to find out more about
microsoft projects courses and other Microsoft training courses.

Ms project tip:

Email a Task

When you need to communicate important information to your project staff use Microsoft Project 2003 to send them a note using outlook or an e-mail system.

1.In a task sheet, select the task or tasks which you want to send a project note.

2.On the File menu, point to Send To, and then select Mail Recipient (as Schedule Note).

3.Under Address message to, select the recipients of your note.