Forum home » Delegate support and help forum » Microsoft Project Training and help » Microsoft Project
Microsoft Project
Resolved · Low Priority · Version 2003
John has attended:
Project Intro Intermediate course
Microsoft Project
How do I change my task dates?
For upcoming training course dates see: Pricing & availability
RE: Microsoft Project
Hi John
Thanks for your question - you can double click on a task and go to the advanced tab. From here you can set a task constraint (such as start no earlier than) to position your task on the Gantt chart.
Hope this is helpful - do let us know if you have any other questions.
Kind regards,