Resources

resolvedResolved · Low Priority · Version 2003

replyReply Tue 27 May 2008, 16:41Delegate Ian said...

Ian has attended:
Project Intro Intermediate course
Project Intermediate course

Resources

I need to add more resources doing different related task working towards a common goal

For upcoming training course dates see: Pricing & availability

replyReply Fri 20 Jun 2008, 16:07Trainer Andrew said...

RE: resources

Hi Ian

Thanks for your question. You can add more resources to a task by splitting the screen (window > split), choosing the task in question then in the lower left corner of the screen choosing your resources. Be careful though about adjusting tasks that already have resources. Project may adjust your task's duration. Check whether effort driven scheduling is enabled as well as the current task type - the controls are in the centre of the screen just below the split bar.

If you have any further questions please don't hesitate to let us know.

Kind regards,

Andrew

 

Please browse our web site to find out more about
microsoft+project+courses and other Microsoft training courses.

Ms project tip:

Enter a Date

You can enter today's date (or tomorrow's date) in a date field, by simply typing in the word 'today'or 'tomorrow' and Project will insert the date for you.

View all MS Project hints and tips


Microsoft Certified Partner Accredited Training Provider: Institute of IT Training Institute of Leadership and Management - Certified Courses Security Seal verified by visa, mastercard securecard