Exporting

resolvedResolved · Low Priority · Version 2007

replyReply Thu 29 May 2008, 17:13Delegate Martin said...

Martin has attended:
Project Intermediate course

Exporting

How do I export information from Project to Excel?

Thanks

For upcoming training course dates see: Pricing & availability

replyReply Wed 4 Jun 2008, 14:51Trainer Andrew said...

RE: Exporting

Hi Martin

thanks for your question. The quickest way to get your data from Project to Excel is to select the relevant rows in Project, choose Edit > Copy Task then paste straight into Excel.

For a more structured approach you can choose File > Save as and set the type to Excel Workbook. Choose OK and follow the export wizard to choose the fields of data you'd like to export to Excel.

I hope this helps - let us know if you have any other questions.

Kind regards,

Andrew

 

Please browse our web site to find out more about
microsoft project courses and other Microsoft training courses.

Ms project tip:

Format individual bars on your GANTT chart

To draw attention to a bar on your Gantt chart simply double click it. From the dialogue box that opens make your selection of text and bar modifications.

View all MS Project hints and tips


Microsoft Certified Partner Accredited Training Provider: Institute of IT Training Institute of Leadership and Management - Certified Courses Security Seal verified by visa, mastercard securecard