summary not whole number
The UK's Number 1 for Microsoft Office Training Add this page to your favourites/bookmarksBookmark page
 
View printable version of pagePrintable version
Plus One Google
Customer: Sign in
Delegate: Sign in
Trainer: Log in

Forum home » Delegate support and help forum » Microsoft Project Training and help » Summary not whole number

Summary not whole number

resolvedResolved · Low Priority · Version 2007

replyReply Tue 3 Jun 2008, 14:28Delegate anthony said...

anthony has attended:
Project Introduction course

Summary not whole number

I have set up a series of taks and summaries.

I am now going through updating my progress using the 'Actual Duration' column.

I am inputting whole days into this column (i.e. task=project setup; actual duration=3d) but the some summaries are registering this in part days (i.e. 1.47 days).

Why is this? I am not using resourcing and all the tasks are non-effort-driven.

Thanks

For upcoming training course dates see: Pricing & availability

replyReply Fri 13 Jun 2008, 12:55Trainer Stephen said...

RE: Summary not whole number

Hi Anthony

Thank you for your question

This is very hard to answer without actually having sight of you plan. There are a number of possible causes, and we have to consider several variables

Can I suggest that you email me a copy of the plan. this would allow me to quickly see the nature of the problem and come up with a solution.

My email is stephenATmicrosofttraining.net.

Regards

Stephen

replyReply Mon 16 Jun 2008, 09:11Trainer Stephen said...

RE: Summary not whole number

Hi Anthony

Thank you for your question, and subsequent supply of example file.

The issue here is how project calculates the actual duration of a group of tasks, when the group contains a series of complex relationships.

If the group contains a series of tasks linked concurrently start to start, then the calculation will be fairly straightforward and is usually just the sum of the individual tasks.

However, as is the case here, when you have tasks with other types of dependency; i.e start to start, the calculation is much more complex; and project has to calculate a form of average for the group total. This is the case as some tasks will run concurrently, some sequentially and some will overlap

In your case, while project is calculating the total "correctly" it is a pretty meaningless figure, and my advice would be to ignore it. If you need to see actual durations, then just focus on the actual durations of individual tasks. You could even create a view of your Gantt chart that filters out the outline tasks. If you wish to have some idea as to the progress on your outline tasks, then I would suggest "% Complete" is a better indicator.

Hope this is useful

If you have any further queries please do not hesitate to get in touch

Regards

Stephen

 

Please browse our web site to find out more about
ms project training courses and other Microsoft training courses.

Ms project tip:

Use Autofill in MS Project

a. Complete 1st entry
b. Select cell with entry to be copied
c. Click & drag autofill handle over the lines to also contain the same information. (the autofill handle is the little black square in the bottom right hand corner of the heavy lack outline on the selected cell)

View all MS Project hints and tips


Microsoft Certified Partner Accredited Training Provider: Institute of IT Training Institute of Leadership and Management - Certified Courses Security Seal verified by visa, mastercard securecard