Project

resolvedResolved · High Priority · Version 2003

replyReply Tue 24 Jun 2008, 16:11Delegate Louise said...

Louise has attended:
Project Intro Intermediate course

Project

As an event manager I have a deadline that I have no choice but to meet, i.e. the event date. Is it o.k for me to set the project up so that it HAS to end on the event date no matter what? So, all tasks can be flexible but must be completed by event date.

For upcoming training course dates see: Pricing & availability

replyReply Fri 11 Jul 2008, 17:33Trainer Alan said...

RE: Project

Yes. Bear in mind however that when something slips in the Project you will receive warning messages that Project cannot honour the MUST FINISH ON constraint and will have to adjust the schedule yourself in order to keep the constraint in place. This means tight monitoring of the schedule while tracking.

 

Please browse our web site to find out more about
ms project server training and other Microsoft training courses.

Ms project tip:

Change default view – Project 2010

a. In Project, click on the File tab
b. Select General from left hand side (this should be the screen displayed by default)
c. Set the Default view dropdown box to your chosen option
d. Click OK to apply your changes