Microsoft project

resolvedResolved · Low Priority · Version 2003

replyReply Mon 4 Aug 2008, 16:28Delegate Mark said...

Mark has attended:
Project Intro Intermediate course

Microsoft project

please confirm /advise in respect of the creation of float and slack and milestones/constraints

For upcoming training course dates see: Pricing & availability

replyReply Tue 5 Aug 2008, 09:13Trainer Andrew said...

RE: microsoft project

Hi Mark

Float is created where two tasks are linked (e.g. finish to start) and the successor is constrained beyond the finish of its predecessor. A partial constraint type is Start no earlier than SNET (reached via double clicking on the successor name then choosing the advanced tab). The successor could be a task or a milestone (0 duration).

I hope this helps. Do let us know if you have any further questions - kind regards, Andrew

 

Please browse our web site to find out more about
microsoft project training course and other Microsoft training courses.

Ms project tip:

Gantt Charts

Gantt Charts was first Invented by Henry Gantt (1861-1919) while planning the construction of U.S. Navy ships during WWI.hence the name Gantt Charts