ms project london - project start date
The UK's Number 1 for Microsoft Office Training Add this page to your favourites/bookmarksBookmark page
 
View printable version of pagePrintable version
Plus One Google
Customer: Sign in
Delegate: Sign in
Trainer: Log in

Forum home » Delegate support and help forum » Microsoft Project Training and help » ms project london - Project Start Date

ms project london - Project Start Date

resolvedResolved · Low Priority · Version Standard

replyReply Tue 13 Feb 2007, 12:43Delegate Ruth said...

Ruth has attended:
Project Intro Intermediate course

Project Start Date

How do I move a project start date to a date before the current date?

For upcoming training course dates see: Pricing & availability

replyReply Fri 16 Feb 2007, 13:40Trainer David said...

RE: Project Start Date

select project from the menu, project information, choose start date and select from the calendar the date you wish to start from.

 

Ms project tip:

Keep constraining dates to a minimum

As far as possible avoid fixing the dates of your tasks. For example try to steer of clear dragging task bars in the Gantt chart to move them on the timeline or entering dates directly into the Start / Finish fields.

Date constraints such as these limit Microsoft Project's ability to automatically adjust your project whenever you add, remove or modify the duration of your tasks. Instead use the logic in your task dependencies that link your tasks to enable Project to calculate the start and finish dates for you.