Updating
What is the best way to change dates on an existing project planFor upcoming training course dates see: Pricing & availability
RE: Updating
Hi NarinderA good way to change dates on your tasks, especially if you have saved a baseline is to select your task then go to Tools > Tracking > update tasks and record what really happened (actual start or finish). Alternatively if the task is not yet complete but needs to be rescheduled you could try either adding a partial constraint (start no earlier than) to the task so it falls on the correct date or extend the lag on its predecessor relationship.
Hope this helps - do let us know if we can assist further.
Kind regards,
Andrew
|
|