Baselines

resolvedResolved · Low Priority · Version 2003

replyReply Tue 14 Oct 2008, 17:06Delegate Stewart said...

Stewart has attended:
Project Intro Intermediate course

Baselines

how do you set more than 1 baseline then view them simultaneously?

For upcoming training course dates see: Pricing & availability

replyReply Fri 17 Oct 2008, 17:00Trainer Andrew said...

RE: baselines

Hi Stewart

You can save more than one baseline by going to tools > tracking > save baseline and from the top baseline drop-down choosing the baseline field to store your current plan.

You can see more than one baseline by going to the view menu and choosing more views then selecting multiple baselines Gantt (which shows up to 4)

I hope this is helpful - let us know if you have any further questions.

Kind regards,

Andrew

 

Please browse our web site to find out more about
ms project server 2007 course in uk and other Microsoft training courses.

Ms project tip:

Project Community

in the help menu type "Tips" then select "Ask the Project community" this takes you into microsofts site where you can ask questions to lots of knowledgeable people.They make up an online group of experienced Project users who answer questions and provide solutions and tips.

View all MS Project hints and tips


Microsoft Certified Partner Accredited Training Provider: Institute of IT Training Institute of Leadership and Management - Certified Courses Security Seal verified by visa, mastercard securecard