Forum home » Delegate support and help forum » Microsoft Office general help » CPM

CPM

resolvedResolved · Low Priority · Version 2003

replyReply Fri 17 Oct 2008, 15:43Delegate Rebekah said...

Rebekah has attended:
Project Management course

CPM

What is the critical path method and how should I use it?

For upcoming training course dates see: Pricing & availability

replyReply Mon 20 Oct 2008, 16:18Trainer Andrew said...

RE: CPM

Hi Rebekah

Thanks for your question. The Critical Path Method is a way of finding out the earliest date your project can be delivered and also identifies those tasks that have no slack or float around them and also determine the end date of the project.

After creating a network diagram for your project you would then work out:

Earliest Start ES
Earliest Finish EF
Latest Start LS
Latest Finish LF

for each of your tasks.

Step 1 Forward Pass:
Work out the ES for each of your tasks, starting left to right.
A task's ES is the sum of its predecessor durations.

The EF can be calculated as ES + activity duration

Step 2 Backward Pass:
The LF is the latest date the activity can finish without affecting the end date of the project. This process starts at the end of the project and works back toward the start.

The LS is the LF - activity duration

Step 3
You can now calculate float within your project.
Float is LF - EF

The advantage of applications such as Microsoft Project is that they calculate all of this automatically for you and can highlight the critical path directly on the Gantt Chart.

I hope this helps. do let us know if you have any other questions.

Kind regards,

Andrew

 

Please browse our web site to find out more about
time management courses - london and other Microsoft training courses.

Microsoft office tip:

Viewing the whole dropdown menu bar

If you dont like having to point to the double chevron to see the full menus, you can click on Tools, Customise and the options tab.

Clci on Always show full menus to see the full drop down menu bar.

View all Microsoft Office hints and tips


Microsoft Certified Partner Accredited Training Provider: Institute of IT Training Institute of Leadership and Management - Certified Courses Security Seal verified by visa, mastercard securecard