What is a baseline

resolvedResolved · Low Priority · Version 2003

replyReply Fri 31 Oct 2008, 16:03Delegate steve said...

steve has attended:
Project Intermediate course

What is a baseline

what is a baseline

For upcoming training course dates see: Pricing & availability

replyReply Mon 3 Nov 2008, 11:48Trainer Andrew said...

RE: what is a baseline

Hi Steve

Thanks for your question. The baseline captures values for your tasks (Start, Finish, Duration, Work and Cost) so that you can compare your live project position for each of those values with those agreed at the project start.

The baseline can be saved by going to Tools > Tracking > Save baseline and quickly viewed by going to the Tracking Gantt view.

I hope this helps - let us know if you have any further questions.

Kind regards,
Andrew

 

Please browse our web site to find out more about
microsoft/project/courses and other Microsoft training courses.

Ms project tip:

Giving Someone a Gantt Chart Snapshot

To pass on a picture of a Gantt chart segment, choose the appropriate view, select the rows to be included, then click on the camera icon and select For Screen. The graphics image can be pasted into another document. (See Paste icon forn Project 2010)

View all MS Project hints and tips


Microsoft Certified Partner Accredited Training Provider: Institute of IT Training Institute of Leadership and Management - Certified Courses Security Seal verified by visa, mastercard securecard