Project

How can I use negative lag to keep to my base line

For upcoming training course dates see: Pricing & availability

replyReply Mon 3 Nov 2008, 11:57Trainer Andrew said...

RE: project

Hi Ross

Thank you for your question - welcome to the forum!

Negative lag or lead time can be used to refine the model represented by your Gantt Chart.

Either double clicking a successor task name and choosing the predecessor tab or double clicking on the the arrow that connects successor and predecessor takes you to a dialog box that allows you to enter postive or negative lag.

Negative lag brings the sucessor task earlier in the plan and is often used to represent starting tasks earier than scheduled in order to bring a project back into line with its baseline.

I hope this helps - let us know if you have any further questions.

Kind regards,
Andrew

 

Please browse our web site to find out more about
2002 microsoft project training and other Microsoft training courses.

Ms project tip:

Email a Task

When you need to communicate important information to your project staff use Microsoft Project 2003 to send them a note using outlook or an e-mail system.

1.In a task sheet, select the task or tasks which you want to send a project note.

2.On the File menu, point to Send To, and then select Mail Recipient (as Schedule Note).

3.Under Address message to, select the recipients of your note.

View all MS Project hints and tips


Microsoft Certified Partner Accredited Training Provider: Institute of IT Training Institute of Leadership and Management - Certified Courses Security Seal verified by visa, mastercard securecard