Hi Karen
Thanks for your question. You can move the start date for your project by going to the Project > Project Information menu.
Once you have a schedule planned (but before you record progress) you can adjust your project, preserving any float, by switching on the Analysis toolbar (View > Toolbars > Analysis), clicking on Adjust dates and then entering a new date for your project.
I hope this helps - do let us know if you have any further questions.
Kind regards,
Andrew