Summary Tasks
If you've made a mistake with a summary task, what is the quickest way to include another task to the sub-tasks?
For upcoming training course dates see: Pricing & availability
RE: Summary Tasks
Hi Marc,
Thank you for your question.
If you have created a summary task and missed out a task, select the missing task (which should be directly underneath the last sub task) and click the Indent button on the Outline toolbar. This will add the selected task as another sub task.
I hope this answers your question.
Regards
Simon
|