how can i make red(critical) bars not critical,i done 3 phases the same and project made the last one red(critical)
mark
For upcoming training course dates see: Pricing & availability
RE: project
Hi Mark
Project calculates the critical tasks in your project as those that influence the end date of your plan and have no slack or float (that is a change in critical tasks will directly change your end date)
If you'd rather not see the critical path you can work in the Gantt View. By default the critical path is displayed in the Tracking Gantt view.
I hope this helps - let us know if you have any further questions.
Kind regards,
Andrew
Fri 12 Dec 2008: Automatically marked as resolved.
|