When setting up multiple tasks which all have the same duration, how do I update the duration for all tasks at the same time instead of having to go in and update each one individually?
For upcoming training course dates see: Pricing & availability
RE: Task information
Hi Alison
Thanks for your question. Try this:
Highlight the tasks you would like to update by selecting them. Right click on the highlighted tasks and choose Task information. In the general tab set the duration you want and click OK. All tasks should now have the duration you entered.
I hope this helps - let us know if you have any further questions.
Kind regards,
Andrew