projectcustom fields
The UK's Number 1 for Microsoft Office Training Add this page to your favourites/bookmarksBookmark page
 
View printable version of pagePrintable version
Plus One Google
Customer: Sign in
Delegate: Sign in
Trainer: Log in

Forum home » Delegate support and help forum » Microsoft Project Training and help » Project-Custom Fields

Project-Custom Fields

resolvedResolved · Urgent Priority · Version 2003

replyReply Fri 21 Nov 2008, 22:48Delegate Jhun said...

Jhun has attended:
No courses

Project-Custom Fields

Hi Good Day,

I was wondering how you can use the Custom Fields to view cost.

For Example:

1. I need to see the total Cost Value for All resources on that task.

2. And I want that total cost value for all resources be subtracted to the allocated budget so that I could check the remaining budget for that task.

And another question.

If its possible the whole task\subtask moving the dates quickly so that I could not move them one by one manually.

thank you.

For upcoming training course dates see: Pricing & availability

replyReply Mon 24 Nov 2008, 10:08Trainer Andrew said...

RE: Project-Custom Fields

Hi Jhun
Thanks for your questions.
The fields you are looking for are already set up in Project. Try the following and see if it provides the information you are looking for:
In the Gantt Chart view add the cost field (right click on the Task Name column and from the short menu that comes up choose insert column - from the dialog box replace the ID field with the Cost field and click OK)

To make comparisons with budget figures assign your resources to your tasks then just before your project starts save the baseline (tools > tracking > save baseline)

You can now insert the baseline cost, actual cost, and cost variance columns to see what you planned to spend (baseline cost), what you have spent so far (actual cost) what you will spend based on your revised plan (cost) and the difference between what you will spend and your original budget (cost variance)

With regard to your third question the key to Project updating your plan easily is to use links between your tasks and keep fixed dates to a minimum - that way when you change one task Project will reschedule anything impacted by that change for you automatically.

I hope this helps - let us know if you have any further questions.

Kind regards,
Andrew

Mon 1 Dec 2008: Automatically marked as resolved.

 

Please browse our web site to find out more about
2003 microsoft project server and other Microsoft training courses.

Ms project tip:

Avoid Accidental Constraints

The initial default table is the Entry table. Enter a task name and duration, but do not enter start or finish dates. Form the plan using links, predecessors. Typing dates introduces constraints. To remove these constraints, double click on a task, and on the Advanced page of Task Information set the constraint back to As Soon As Possible (all other options are there too.)

View all MS Project hints and tips


Microsoft Certified Partner Accredited Training Provider: Institute of IT Training Institute of Leadership and Management - Certified Courses Security Seal verified by visa, mastercard securecard