Is there any way of showing the task names above he lines in the gant chart?
For upcoming training course dates see: Pricing & availability
RE: office project
Hi Steven
Thanks for your question.
You can put the task names above the bars by going to format > bar styles.
Click on the Task entry (first on the list) and choose the Text tab at the bottom of the dialog box.
You will see there are five slots covering text positions around and inside the bars.
Click in the slot beside the row labelled Top and in the drop down box choose the name field and click OK.
Hope this helps - let us know if you have any further questions.