Any way of configuring Project2007, to allow other types of resource.
Or having differnt sorts of units apart form time, cost,....is it possible to confirgure tohave 'Kilograms' for instance?
For upcoming training course dates see: Pricing & availability
RE: Configuration of formats
Hi Gordon
Thanks for your question. The resource types are fixed as are the time and cost variables used for scheduling however if you want to track material resources you can specify a material label (e.g. Kg, m3, per unit of material used) to suit your requirements.
I hope this helps - let us know if you need any further information.