MS Project

resolvedResolved · Low Priority · Version 2007

replyReply Mon 1 Dec 2008, 15:58Delegate Ida said...

Ida has attended:
Project Introduction course
Project Intermediate course

MS Project

How do I change the project start date?

For upcoming training course dates see: Pricing & availability

replyReply Mon 1 Dec 2008, 16:56Trainer Andrew said...

RE: MS Project

Hi Ida

Thanks for your question. You can specify the estimated start date for your project by going to the Project menu and choosing Project Information.

I hope this helps - let us know if you have any further questions.

Kind regards,
Andrew

Mon 8 Dec 2008: Automatically marked as resolved.

 

Please browse our web site to find out more about
2003+microsoft+project+server and other Microsoft training courses.

Ms project tip:

Giving Someone a Gantt Chart Snapshot

To pass on a picture of a Gantt chart segment, choose the appropriate view, select the rows to be included, then click on the camera icon and select For Screen. The graphics image can be pasted into another document. (See Paste icon forn Project 2010)