Project
Resolved · Low Priority · Version 2003
For upcoming training course dates see: Pricing & availability
RE: Project
Hi Linda
Thanks for your question. The baseline captures values relating to your activities (including start, finish, duration, work and cost) so that you can compare your starting and current positions to identify slippage.
The tracking Gantt view (View > Tracking Gantt) shows the baseline below your live project as grey task bars.
I hope this helps - let us know if you have any further questions.