Forum home » Delegate support and help forum » Microsoft Project Training and help » microsoft project courses london - How do i adjust subtask dates and make the main task dates follo

microsoft project courses london - How do i adjust subtask dates and make the main task dates follo

resolvedResolved · Low Priority · Version Standard

replyReplyFri 23 Feb 2007, 12:43Delegate Nick said...

How do i adjust subtask dates and make the main task dates follo

When i add a subtask and i change the date, the main task dates do not adjust to show the changes.

For exampe; if i increase the number of days of the subtask, the main task still shows the original dates, even though the subtask finishes at a later date.

Can anyone tell me how i can change it back, so that when i adjust the dates of my subtasks the main task follows suit?

Thanks

For upcoming training course dates see: Pricing & availability

replyReplyThu 1 Mar 2007, 16:11Trainer Jacob said...

RE: How do i adjust subtask dates and make the main task dates f

Hi Nick

This might be obvious, but best to check> Have you indented the task, so it is a subtask? If you just have one subtask, then yes when you vary the duration this will be reflected in the main task.

However if you have more than one subtask and they are not linked, then by default the duration of your main task depends on the greatest duration set to your subtasks (on account that all subtasks start at the same time).

Does this help?

Rgds

Jacob

replyReplyThu 1 Mar 2007, 16:54Delegate Nick said...

RE: How do i adjust subtask dates and make the main task dates f

I have resolved the problem,

I did have it as a subtask but the subtask dates were not reflected in the duration of the main task. For example my subtask was 5 days and the main task only shows a duration of 1 day.

I resolved it by going to the tools tab, choosing options, selecting the calculations tab and then selecting 'Automatic' for the caculation mode.

The problem was that i had 'manual' selected for some reason. With it on Manual you can change subtask dates and they do not effect the length of the main task.

Sorted now but thanks.

 

 

Ms project tip:

Avoid Accidental Constraints

The initial default table is the Entry table. Enter a task name and duration, but do not enter start or finish dates. Form the plan using links, predecessors. Typing dates introduces constraints. To remove these constraints, double click on a task, and on the Advanced page of Task Information set the constraint back to As Soon As Possible (all other options are there too.)

View all MS Project hints and tips

forum postHow do you link multiple projects?

» Forum post: Linking to


Rate this page:
2.2/5 (213 votes cast)
Accredited Training Provider: Institute of IT Training Institute of Leadership and Management - Certified Courses
Microsoft Certified Partner
Security Seal verified by visa, mastercard securecard

Mini sitemap. These are the main areas of our web site. Full sitemap.

Management training

Professional Skills courses
Project Management Course London
Project Management Courses London
Project Management Training London
Project Management Training
Project Seminar
Project Seminars
Time Management Course London
Time Management London
Time Management Courses London
Time Management Training London
Introduction to Finance course
Assertiveness Skills course
Effective Communications Skills training
Presentation Skills London

Training Formats

Public scheduled courses
On-site training
Closed company courses

Consultancy
Application Development

Blogs

Excel Training
MS Project Training
Microsoft Training Blog

Version differences

Office 2010 vs 2007
MS Project version differences

Training Information

London Computer Training
Computer Training London
Docklands Training Courses
Docklands Training London

Training venues London
Client list
FAQ
Pricing and availability
Course details / Syllabus

Training Articles
Training Information

Microsoft training

Microsoft Office training
& IT Applications

Microsoft Project training
Microsoft Outlook training
Microsoft Powerpoint training
Microsoft Word training
MS Project courses
MS Project training
Outlook courses
PowerPoint courses
PowerPoint training
VBA courses
Word courses
Microsoft.training
(more...)

Excel Training

Excel courses
Excel Training Courses Medway
Autonumber in Excel
Microsoft Excel training
Basic Excel Courses
Basic Excel Course
Basic Excel Training

Interested in MS Access training?

Access courses
Microsoft Access training
Microsoft access courses
Microsoft training access course
Microsoft+access+training
Access courses in london

Training provider

Training providers
IT training companies
IT training providers
Management Training providers
Management Training provider

Event history, feedback results
Events in 2012 · 2011 · 2010 · More

See also

Crystal Reports training