replyReply Wed 10 Dec 2008, 16:32Delegate Kelly said...

PROJECT

How do you change one task/resource so that you can set muultiple calendars to it. ie. the task runs mon to fri (@

For upcoming training course dates see: Pricing & availability

replyReply Sun 11 Jan 2009, 18:45Trainer Simon said...

RE: PROJECT

Hi Kelly,

Thank you for your question.

After speaking to my colleagues, set the resource calendar to work on that saturday.

Then go to resource sheet and double click on the resource in question. Go to the Costs tab and set an effective date in the second row for the saturday in question and put the rate of 60 per hour in Cost Rate table A.

Then you need to set the original 50 per hour back by typing in sundays date(next day) in the third row, which means any work assigned will switch back to the original rate.

I hope this answers your question.

Regards

Simon

Mon 19 Jan 2009: Automatically marked as resolved.

 

Please browse our web site to find out more about
2003.microsoft.project.server and other Microsoft training courses.

Ms project tip:

Project Community

in the help menu type "Tips" then select "Ask the Project community" this takes you into microsofts site where you can ask questions to lots of knowledgeable people.They make up an online group of experienced Project users who answer questions and provide solutions and tips.

View all MS Project hints and tips


Microsoft Certified Partner Accredited Training Provider: Institute of IT Training Institute of Leadership and Management - Certified Courses Security Seal verified by visa, mastercard securecard