Gantt charts
Resolved · Urgent Priority · Version 2003
Richard has attended:
No courses
Gantt charts
Does anybody know how to copy a whole Gantt chart, (Tasks and timelines) into a spreadsheet?
Thanks, Richard
For upcoming training course dates see: Pricing & availability
RE: Gantt charts
Hi Richard
Thank you for your question
It is possible to copy the tasks into excel using the Save as Excel Spreadsheet option.
This however will not copy across the task bars as Excel has no way to visualise them. It might be possible to write a macro in Excel to create the task bars, but this would be a substantial undertaking
Regards
Stephen
|