MS Project

resolvedResolved · Low Priority · Version 2000

replyReply Fri 16 Jan 2009, 15:33Delegate Christopher said...

Christopher has attended:
Word Introduction course
Outlook Introduction course

MS Project

Does MSP have an auto sort function?

For upcoming training course dates see: Pricing & availability

replyReply Wed 28 Jan 2009, 12:42Trainer Andrew said...

RE: MS Project

Hi Christopher

Project does enable you to sort your plan. From the Project menu choose Project > Sort and then choose one of the built in sort fields or click on sort by... to select your own sort fields.

I hope this helps - do let us know if you have any more Project questions.

Kind regards,
Andrew

Tue 3 Feb 2009: Automatically marked as resolved.

 

Please browse our web site to find out more about
microsoft-project-server-training and other Microsoft training courses.

Ms project tip:

Inserting Task Durations Quickly

When entering durations for your tasks simply use the single letters - m for min, h for hr, d for day, w for week, but mon for month. If default is set for days, you need only type the number, for example 3 for 3days, or 0.5 for half a day.

View all MS Project hints and tips


Microsoft Certified Partner Accredited Training Provider: Institute of IT Training Institute of Leadership and Management - Certified Courses Security Seal verified by visa, mastercard securecard