Forum home » Delegate support and help forum » Microsoft Project Training and help » MS Project
MS Project
Resolved · Low Priority · Version 2003
Steve has attended:
Project Introduction course
Project Intermediate course
MS Project
How do I charge for my time?
For upcoming training course dates see: Pricing & availability
RE: MS Project
Hi Steve
Thanks for your question.
If you add a standard rate to a resource in the resource sheet and then assign the resource to a task Project will calculate the rolled up cost of the task. In the Gantt view you can see the cost by inserting the cost field in the table [right click on a column header and choose insert column - then choose the cost field] .
I hope this helps let me know if you have any further questions.
Kind regards,
Andrew
Tue 3 Feb 2009: Automatically marked as resolved.
|