Milestone
How best to identify a milestone, & what is their purpose?For upcoming training course dates see: Pricing & availability
RE: Milestone
Hi KarenA milestone is used to indicate a particular point in your project's life. To create a miletone in Project just add a task an set its duration to zero. Project redraws the the task on the Gantt chart as a black diamond plus its start date.
Milestones are useful to clearly indicate key dates in your project.
Hope this is helpful - contact us again if you have any further questions.