Adding a milestone

resolvedResolved · Low Priority · Version 2003

replyReply Thu 29 Jan 2009, 16:49Delegate Jennifer said...

Jennifer has attended:
Excel Advanced course
Project Intro Intermediate course

Adding a milestone

How do I add a milestone?

For upcoming training course dates see: Pricing & availability

replyReply Fri 30 Jan 2009, 09:26Trainer Andrew said...

RE: Adding a milestone

Hi Jennifer

Thanks for your question - to add a milestone create a task and set its duration to zero. The task on the chart becomes a diamond symbol with a date attached.

I hope this helps - do let us know if you have any further questions.

Kind regards,
Andrew

 

Please browse our web site to find out more about
ms-project-course and other Microsoft training courses.

Ms project tip:

Gantt Charts

Gantt Charts was first Invented by Henry Gantt (1861-1919) while planning the construction of U.S. Navy ships during WWI.hence the name Gantt Charts

View all MS Project hints and tips


Microsoft Certified Partner Accredited Training Provider: Institute of IT Training Institute of Leadership and Management - Certified Courses Security Seal verified by visa, mastercard securecard