Project - Gantt bar

resolvedResolved · Low Priority · Version 2000

replyReply Fri 30 Jan 2009, 15:44Delegate Alan G said...

Alan G has attended:
Project Intermediate course

Project - Gantt bar

Is there a way of expanding the depth of a bar?

For upcoming training course dates see: Pricing & availability

replyReply Sun 1 Feb 2009, 11:23Trainer Simon said...

RE: Project - Gantt bar

Hi Alan,

Thank you for your question.

As far as I am concerned there is no way of expanding the depth of the bar. You can ony change the style of the bars through Format Bar Styles.

I hope this answers your question.

Regards

Simon

 

Please browse our web site to find out more about
training in microsoft project and other Microsoft training courses.

Ms project tip:

Link tasks using predecessor column - project

a. First, note ID number of the task you want to link to (predecessor). Then, in the predecessor column of the task you want to link to (successor), type the predecessor task's ID number.
b. The link will be a Finish to Start (the default type).
c. Or you can add in a code for a different relationship type
i. SS = Start to Start
ii. FF = Finish to Finish
iii. SF = Start to Finish
d. You don't have to type the task ID numbers in any specific order, but you must separate multiple tasks with commas.

View all MS Project hints and tips


Microsoft Certified Partner Accredited Training Provider: Institute of IT Training Institute of Leadership and Management - Certified Courses Security Seal verified by visa, mastercard securecard