What is the relationship between DURATION and WORK CONTENT.
For upcoming training course dates see: Pricing & availability
RE: Project 2007
Hi Norman
Thank you for your question. The Duration represents how long you will allow for something to take place and Work represents the amount of activity that resources will carry out during that time.
For example you might allow 5 days duration to produce a report. During that time the total work required might be 10 hours.
I hope this helps - do let us know if you have any further questions.