MS Project 2003 - Using a Workspace

resolvedResolved · High Priority · Version 2003

replyReply Tue 17 Feb 2009, 17:11Delegate Katherine said...

Katherine has attended:
Project Intro Intermediate course

MS Project 2003 - Using a Workspace

I have been trying o use the workspace function for ease as I have a Master project with subs however, I follow the instruction in the 2003 Intermediate Manual and it comes up with 'Operation Failed!'.

Am I doing something wrong - is it because some of the projects I want to open are on different places on a network? Or generally is the workspace function a waste of time?
Thanks
K

For upcoming training course dates see: Pricing & availability

replyReply Thu 19 Feb 2009, 12:41Trainer Andrew said...

RE: MS Project 2003 - Using a Workspace

Hi Katherine

Thanks for your question. In principle the workspace feature should make it easy to open several projects at the same time.

To save a workspace first open and arrange your plans then from the File menu choose save workspace.

In future when you double click the workspace file MS Project will re-open and arrange your selected files.

If you find you are having problems follow this process with just two files. Once you are happy that it works you go ahead and save a workspace with the files you need.

I hope this helps - do let us know if you have any further questions.


Kind regards,
Andrew

Thu 26 Feb 2009: Automatically marked as resolved.

 

Please browse our web site to find out more about
microsoft projects courses and other Microsoft training courses.

Ms project tip:

Typing Links Between Tasks

In the Entry table, use the Precessors column to type in links. Type the previous task's ID to link. To change the link, add FS (Finish-Start), FF (Finish-Finish), and so on, and + duration to add a Lag, or - duration for a Lead time. Example: for task 5, 4FS+1w ... task 4 preceeds task 5, finish to start, with a week lag between.

View all MS Project hints and tips