Forum home » Delegate support and help forum » Microsoft Project Training and help » Start/Finish columns - leaving blank whilst having data in subse

Start/Finish columns - leaving blank whilst having data in subse

resolvedResolved · Urgent Priority · Version 2003

replyReply Fri 13 Mar 2009, 11:29Delegate Amy said...

Amy has attended:
No courses

Start/Finish columns - leaving blank whilst having data in subse

Hi

I have different bar styles assigned to different start/finish columns.

Therefore I want to enter dates in different columns relevant to each task, and many columns will not have data in the first start/finish columns (un-numbered).

However, I can't seem to delete dates from the first start/finish columns or insert NA. It always reverts to having the date of the start of the project.

Any help welcomed

Thanks

For upcoming training course dates see: Pricing & availability

replyReply Sun 15 Mar 2009, 21:14Jack (guest) said...

RE: Start/Finish columns - leaving blank whilst having data in s

Amy,

These would be the default Start and Finish dates. It makes sense that you are not able to delete the data within these cells.

I don't fully understand what you are trying to achieve by manually altering these dates, but you could always format the font to white so the dates could not be seen within the cells....or....hide those two columns all together.

Either way would work to meet your needs described above. But with that said, I'm really not sure you are using Microsoft Project the way it could best be used.

Hope this helps!
J Black
http://www.pmconnection.com

 

Please browse our web site to find out more about
ms project 2003 courses and other Microsoft training courses.

Ms project tip:

Typing Links Between Tasks

In the Entry table, use the Precessors column to type in links. Type the previous task's ID to link. To change the link, add FS (Finish-Start), FF (Finish-Finish), and so on, and + duration to add a Lag, or - duration for a Lead time. Example: for task 5, 4FS+1w ... task 4 preceeds task 5, finish to start, with a week lag between.