Forum home » Delegate support and help forum » Microsoft Project Training and help » Baselines
Baselines
Resolved · Low Priority · Version 2003
James has attended:
Project Intro Intermediate course
Baselines
Can you add the date the baseline was saved anywhere so you can view as part of the gantt? [not as a note]
For upcoming training course dates see: Pricing & availability
RE: Baselines
Hi James,
Thank you for your question.
Unfortunately, as far as I am concerned you cannot show the date the baseline was saved on by inserting a field in the Gantt chart, so maybe a note is the best option.
Alternatively you could create a text box and type the baseline date in there and position the box where you want on the Gannt chart.
I hope this answers your question.
Regards
Simon
Thu 9 Apr 2009: Automatically marked as resolved.
|