What's the difference between a Gantt chart and a tracking Gantt chart?
For upcoming training course dates see: Pricing & availability
RE: MS Project
Hi Anthony
Thank you for your question. Both views show the Gantt chart. The tracking Gantt also highlights the critical path, as well as progress (%) and the baseline (if saved).
I hope this helps - do let us know if you have any further questions.
Kind regards,
Andrew
|